The Rajahmundry facility has been operating at full capacity, and the proposed investment is expected to increase its capacity by 60 percent.
Aug 6, 2025

Andhra Paper Limited has announced its plans to invest INR 178 crore in the upgradation and rebuilding of Paper Machine-3 at its Rajahmundry manufacturing facility. The facility is expected to yield an incremental production up to 60 TPD, currently it has a production capacity of 36,000 TPA. The addition of capacity is in the core area of operations. The proposed capacity is expected to be added in 13 months.
The Rajahmundry facility has been operating at full capacity, and the proposed investment is expected to increase its capacity by 60 percent. The capital is planned to be generated through internal accruals/or bank financing.