Pakka Targets December Start-Up for PM4, Secures Reliance Order for Solar Glass Interleaving Paper

admin
Pakka Limited is advancing Project Jagriti with Paper Machine 4 (PM4) trials underway and commercial production targeted for January 2027, while expanding its specialty paper business through a new Reliance order. Nov 12, 2026 Pakka Limited has completed pilot trials of its FlexC Base paper in Europe, with encouraging results.......
HEADLINE Special Feature

Pakka Shift From ‘Individual Loop Control To Process-Wide Optimization’

admin
In an exclusive interview with Paper Mart, Mr. Jagjeet Singh Khanna, Paper Machine Head, Pakka Limited, shares that traditionally, paper mills depended on operator intervention and PID-based feedback control during the paper production process. Today, the focus is on predictive and integrated control, feedforward strategies, and real-time process data to......
Uncategorized

Paper Mart Emagazine Aug-Sep, 2026

admin
Paper Mart’s Aug–Sep 2026 Edition is Now Live! The Aug–Sep 2026 edition of Paper Mart features an insightful cover story, ‘Controlling Process Variability: Systems for Consistent Papermaking’, examining how paper mills are moving beyond automation of individual processes towards integrated systems designed to minimise variability across the papermaking value chain.......
News

Pakka Limited Advances Project Jagriti with New Paper Machine and Capacity Expansion

admin
Pakka is advancing Project Jagriti at its Ayodhya facility, comprising a new 100 TPD paper machine, capacity expansion of PM-3 and the pulp mill, and an additional 15 MW power plant. As of June 30, 2026, the company had received INR 51.09 crore against preferential issue proceeds of INR 114.62......
News

Pakka Progresses Project Jagriti; PM 4 Commissioning and FlexC Development on Track

admin
Pakka is progressing with Project Jagriti, with major equipment work substantially completed and key commissioning milestones ahead. The company is targeting September 2026 for power and recovery boiler start-up and November 2026 for PM4 commissioning, alongside FlexC development. Aug 18, 2026 Pakka Limited is progressing with Project Jagriti, with around......
News

Pakka Approves Restart of US Subsidiary with USD 1 Million Investment

admin
Pakka Limited has approved the restart of operations at its wholly owned US subsidiary, Pakka Inc., with an aggregate financial outlay of up to USD 1 million. The move aims to clear outstanding liabilities, provide working capital and support the subsidiary’s project.  Aug 14, 2026 Pakka Limited has approved the......
News

Pakka Limited Utilises INR 129.91 Crore for Capacity Expansion Under Project Jagriti 

admin
Pakka Limited will invest INR 129.91 crore in capacity expansion and modernization under its Jagriti Project to strengthen integrated manufacturing operations. May 6, 2026 Pakka Limited has outlined a capital investment of INR 129.91 crore toward capacity expansion and infrastructure development under its ongoing Jagriti Project, as per its latest......
News

Pakka Postpones Project Jagriti Commercial Operations in August 2026

admin
Pakka’s Project Jagriti investment cost has been revised from INR 675 crore to INR 750 crore. The Commercial Operation Date (COD) has been extended from April 1, 2026, to August 1, 2026, due to technical adjustments in machinery and associated infrastructure. Apr 13, 2026 Pakka Limited is implementing the ‘Jagriti......